2021 Falcon Heights Pavement Management Program

Project Schedule


The schedule shown below is weather-dependent and subject to change.

  • Fall – Additional Restoration
  • October 25 – Last day to pay assessments without interest
Please note, staff will review the project area in 2022 to see if any additional restoration is required.

Overview


The City of Falcon Heights manages a comprehensive Pavement Management Program which includes repaving several miles of local streets every two years. To see which streets are being repaved in 2021, please see the proposed 2021 Pavement Management Project map.

All of the proposed roadways will have the top layer of asphalt section removed and repaved. Spot curb repairs will also be done as part of this project. We expect that there will be very little impact to driveways as part of this project.

An infiltration basin will be constructed at the north end of Lindig Street to improve water quality and drainage in the area.
  

Public Process


On September 23, 2020, the City Council accepted the feasibility report and set the public hearing for the project.  A public hearing was held on October 28, 2020, to discuss the project including assessments.  At that meeting the City Council ordered the improvements.  On February 10, 2021, Falcon Heights Council awarded the contract to Molnau Trucking LLC in the amount of $964.222.53.  Bid abstract information is available on Roseville's eGram website.  On September 22, 2021, the City Council held a public hearing and adopted the assessment roll for the special assessment funding of the project.

Private Utility Project


Xcel Energy has notified the City that they will replace existing gas lines in several of the project streets this summer. Their work will take place on the following project streets: Tatum St, Lindig St., St Marys St. and West Snelling Drive.